P. ServiceWater professionals
Project

Condition Assessment, NRW Baselining and Operational Improvement Plan for the Lajjoun-Ghwair Transmission Pipeline

Dar Al-Omran for Infrastructure & Environment (DOI) · Jordan · 2026

Condition Assessment, NRW Baselining and Operational Improvement Plan for the Lajjoun-Ghwair Transmission Pipeline

Sub-contracted to conduct condition assessment for Lajjoun-Ghwair Transmission Pipeline (approximately 20 km) including NRW baselining and operational analysis aimed at identification of water losses that represented in potential illegal-use connections and/ or invisible leaks across the pipeline, along with development of improvement plan that will be substantially optimizing the engineering design process.

Several technologies were deployed such as GPR, correlator, ground microphones, pipe tracers and portable flow & pressure on-site measurements, that concluded with detailed assessment report and operational improvement plan in-line with engineering design phase, along with water losses quantification and performance benchmarking for optimization O&M for the new project.

← Back to all projects

Let's work together

Ready to build more resilient water systems?