P. ServiceWater professionals

DMA establishment and commissioning

District metered areas turn a large, opaque network into zones a utility can measure and manage. We establish, test and commission DMAs that work as designed.

DMAs Establishment & Commissioning for DZ19, DZ46 and DZ21 in Amman
From our project: DMA Establishment in Amman DZ19, DZ46, DZ21
DMA Establishment

DMA services

A district metered area (DMA) is a section of the network with defined boundaries and metered inflows. When a DMA is properly isolated, the utility can compare what goes in with what customers use, and see immediately where losses are rising.

Many DMAs exist on paper but leak across their boundaries through unknown interconnections and open valves. Our field teams verify every boundary with subsurface utility engineering, pressure testing and zero-pressure tests, then commission the DMA against design standards. Our teams have established more than 45 DMAs in Marj Al-Hamam and Naor alone, alongside DMA programs in Amman and Tafila.

  • DMA design review and operational assessment.
  • DMA boundary verification and hydraulic isolation testing.
  • Identification of redundant networks and interconnections with GPR and pipe tracers.
  • Site measurements, zero-pressure tests and performance testing.
  • DMA commissioning in line with utility service delivery standards.
  • DMA pressure monitoring, critical point analysis and pressure management.
  • DMA service chamber refurbishment and bulk meter installation support.
DMA Establishment

Service details

District metered area services

District metered area services from design review to commissioning: we make sure every DMA is isolated, metered and ready to monitor.

DMA boundary verification

Boundary valves are located and tested, interconnections traced with GPR and pipe locators, and zero-pressure tests prove isolation.

DMA pressure monitoring

Pressure loggers at inlets and critical points show whether supply meets service standards and where pressure management can cut leakage.

How we work

Review

We check the DMA design, network records and GIS data before going to site.

Verify

Field crews trace pipes, locate valves and find hidden interconnections.

Test

Zero-pressure and pressure tests prove each boundary is hydraulically isolated.

Commission

We commission the DMA, set up monitoring and hand over a verified boundary.

FAQ

Frequently asked questions

What is a district metered area (DMA)?

A DMA is a discrete zone of a water distribution network, separated by closed valves or cut pipes, with all inflows and outflows metered. It lets the utility monitor consumption and losses zone by zone.

Why do DMAs fail after construction?

Usually because of unknown interconnections, passing valves or incomplete records. Boundary verification and isolation testing find these problems before the DMA is commissioned.

How many DMAs have you established?

Our teams have established and commissioned DMAs in DZ19, DZ46 and DZ21 in Amman (over 40 hydraulic boundaries), more than 45 DMAs in Marj Al-Hamam and Naor, and DMAs in Tafila Governorate.